【摘要】市政公用建設項目中垃圾處理場工程屬市政工程,該項目標段多,工程較復雜,影響因素多,受自然條件和客觀因素的影響大,因此從技術與經(jīng)濟結合,加強投資控制;做好工程記錄,嚴格現(xiàn)場簽證管理;嚴格控制工程變更;加強合同管理、減少對方索賠適時提出反索賠;嚴格控制中間計量;嚴格審定工程結算是在市政工程項目實施階段進行造價控制的主要工作內(nèi)容。
【關鍵詞】市政工程;施工全過程;造價控制
【Abstract】Municipal public works construction project is a municipal waste disposal sites in the project, the project tenders and more, the project is complex, influenced by many factors, by natural conditions and the great impact of objective factors, so from a technical and economic integration, strengthen the investment control; good work record, strict visa-site management; strict control of engineering change; strengthen contract management and timely reduction of the other claims made against claims; strictly control the middle of measurement; strictly audited balance sheet is in the public works project implementation stage of the project cost control of major work content.
【Key words】Municipal engineering; Whole construction process; Cost control
1. 技術與經(jīng)濟結合,加強投資控制
工程造價管理不僅是個工程經(jīng)濟問題,它還綜合了技術與管理方面為一體。市政工程中造價控制人員除要有市政工程和工程造價方面的專業(yè)知識外,還要有一定的測量方面和計算機制圖的知識。下面著重談談土石方工程的計量問題。
工程量清單中土石方工程量由設計院根據(jù)地形圖計算,由于地形變化和采用地形圖的比例等問題,清單的土石方與實際有出入工程單位進場后,由建設、監(jiān)理、施工、造價咨詢四家單位共同進行實地測量的實際工程量作為結算依據(jù)。土石方工程的計量同工程測量緊密相關,測量儀器有全站儀、電子測距儀、電子經(jīng)緯儀,如果造價人員不懂測量知識、測量儀器的使用,以及測量數(shù)據(jù)的計算、繪圖,就沒有起到現(xiàn)場計量控制作用。在現(xiàn)場計量應注意以下幾個方面:
?。?)首先應熟悉測量儀器的使用;
?。?)了解現(xiàn)場內(nèi)控制點的坐標和高程:
(3)在橫斷面上應選擇地面變化較顯著的點作為斷面點,特別是挖方區(qū)標高低的斷面點、填方區(qū)標高和換填區(qū)標高低的斷面點,現(xiàn)場測量中充分利用已復核的控制點進行校核糾正測量的錯誤;
(4)根據(jù)水平距離、水平角、豎直角數(shù)據(jù)計算各測量斷面點的X、Y、Z坐標,校核平面坐標是否在相應斷面上;
?。?)掌握用計算機進行繪圖并計算工程量的方法。
應用一些工程專業(yè)軟件會事半功倍,本人選擇《工程測量數(shù)據(jù)處理系統(tǒng)》作為的工程測繪數(shù)據(jù)處理軟件;現(xiàn)場測量數(shù)據(jù)整理編輯采用MicrosoftExcel表格方式;繪圖軟件采用基于AU